Intercession City–Dundee 230 kV Rebuild
Intercession City to Dundee, Florida, USA
Quanta completed the rebuild 20 miles (34 km) of energized 230 kV transmission line. Single circuit 230 kV wood H-frame structures replaced with double circuit steel poles
- No outage required, while 120 days outage required for de-energized
- Outage results in cost of US$7.5 million.
- Structure replacement done in 150 days due to energized nature
- Avoided potential reliability penalty
Voltage: 230 kV
Completion: 2010
Quanta Team: Dillard Smith Construction, Quanta Energized Services
Services: Energized Services